Hong Kong is fast-tracking Northern Metropolis links. Will they be ready in time?

0

Por Vivian Au — South China Morning Post – News feed

Advertisement Hong Kong economy Hong Kong Transport Hong Kong is fast-tracking Northern Metropolis links. Will they be ready in time?

Completion of Tsing Lung Bridge and San Tin section of main highway brought forward, but experts warn people will be arriving far earlier

3 -MIN READ 3 -MIN Listen

The Hung Shui Kiu/Ha Tsuen New Development Area of the Northern Metropolis, with Shenzhen in the distance. Photo: Karma Lo

Vivian Au Published: 12:00pm, 26 Sep 2026 Hong Kong will fast-track key Northern Metropolis roads, bringing forward the San Tin highway section to 2034 and targeting 2033 for the Tsing Lung Bridge, but a transport expert and lawmaker have cautioned that the first arrivals could still end up stranded.

Infrastructure projects could lag behind developments such as the Hung Shui Kiu University Town, they said, suggesting the government launch express bus routes and build the Central Rail Link as soon as possible to ensure connectivity.

A source told the South China Morning Post that authorities were pushing ahead with the Tsing Lung Bridge project, bringing forward its launch by two years to 2033.

The acceleration of the San Tin section of the planned Northern Metropolis Highway, meanwhile, would mainly be achieved through techniques such as slope stabilisation, the source said.

Select Voice Select Speed 0.8x 0.9x 1.0x 1.1x 1.2x 1.5x 1.75x 00:00 00:00 1x AI-generated voice

Fonte: South China Morning Post – News feed

Deixe um comentário

O seu endereço de email não será publicado. Campos obrigatórios marcados com *